The dashboard shows a color-coded status of each Automated Test Equipment device. It provides a summary of the latest Results if available. The UUID of the Automated Test Equipment device is shown in the box header.

_images/dashboard.png

Results Summary

Passing test plan is green. The date executed is recorded when the Automated Test Equipment interacted with Knilb to perform the test plan. The total number of tests executed is also shown.

Failing test plan is red, indicating at least one test case failed during execution of hte test plan. Click on the UUID in the box header to expand details of the failed test plan execution.

Note

Dashboard does not show status of an in-progress test plan execution. Results are committed after test plan execution.

Yellow Notifications

Missing results are yellow, indicating the Automated Test Equipment does not have test results.